How Long Does It Take to Build and Launch a Mobile App?
Weps Technologies · 20/10/2026 · Updated 12/11/2026
A focused mobile app MVP may fit a 2–4 month planning range and a broader custom project 4–9 months or longer. See where the time goes, how to read an estimate and how store review fits in.

A focused mobile app MVP may fit a 2–4 month planning range, while a broader custom project can take 4–9 months or longer. These are vendor planning ranges, not delivery guarantees (MobiLoud). Check whether design, backend work, testing and store release are included before adding any extra launch allowance.
These are benchmarks, not promises. Almost every published figure comes from agencies, including us, and agencies publish timelines to attract clients. We have said where each number comes from so you can weigh it.
How long does an app take, by type?
The ranges below come from agency breakdowns summarised in our research (MobiLoud and Affective, formerly Glance, among them). The differences mostly come from how each agency defines scope. MobiLoud, for example, includes planning through store approval within its overall ranges (MobiLoud), so use these figures as vendor planning guidance rather than an independent forecast for your project.
| Stage or app type | Typical time |
|---|---|
| Basic prototype | 2 to 6 weeks |
| MVP (first usable version) | 2 to 4 months |
| Standard custom app | 4 to 9 months |
| Existing website converted into an app | About 4 to 8 weeks (one source only) |
Agency estimates for an MVP run from about 6 weeks to 6 months. A range that wide tells you the number depends far more on what you ask for than on who builds it.
How should you read an estimate?
Compare the same start and finish points. A clickable prototype, a testable build, a store submission and a public release are different milestones. Ask which one the estimate promises, and what the estimate includes.
Where does the time actually go?
Building the screens is only one part. Agency breakdowns put the surrounding work at roughly this:
- Discovery and planning: 2 to 4 weeks. This is where you decide what the app must do and what can wait.
- Wireframes and user flows: 1 to 2 weeks for a simple MVP.
- Design and development: the bulk of the project, and the part that stretches most with scope.
- Testing: at least 2 to 3 weeks. Cutting this is how apps launch with bugs that users find first.
- Store submission and review: days to a few weeks, covered below.
People often ask only about development. In practice the planning, testing and release steps are a large share of the calendar.
What makes an app take longer?
Delays usually come from dependencies as much as from coding: integrations, store review, unclear decision ownership, data access, compliance questions and the depth of quality testing. Notice that most of these are not coding problems.
In plain terms, these push a project toward the upper end:
- Payments, because they add security, testing and store rules.
- AI features, which add design, data and testing work.
- Integrations with other systems, especially where you do not yet have access to the data.
- Slow or split approvals, which leave finished work waiting for a decision.
- Building two separate native apps, one for iOS and one for Android.
Adding more developers may help parallel work, but it does not automatically shorten dependent tasks or external approvals.
Is a cross-platform app faster?
A shared codebase can reduce duplicated implementation where Android and iOS requirements are similar. Flutter, for example, supports code reuse while allowing platform-specific integrations (Flutter architectural overview). That capability does not establish a fixed time saving: native integrations, SDK quality, team experience and testing on both platforms still affect the schedule.
If the app depends heavily on camera processing, Bluetooth, background work or other device-specific behaviour, prototype that behaviour before choosing the stack. For many small business apps, such as bookings, orders, simple accounts and notifications, a single cross-platform codebase is often a sensible starting point. We build Android, iOS and cross-platform apps, and which one fits depends on what the app needs to do.
How long does Apple take to review an app?
As checked on 11 November 2026, Apple says it typically reviews at least 50% of submissions in under 24 hours and 90% in under 48 hours (Apple: App Review). These are aggregate review figures, not a deadline or an approval guarantee for your app. Missing information or issues can require further work.
Prepare complete review notes and working access to restricted features, and keep the backend available. Include time for fixes and resubmission where needed, and distinguish approval from the release date you choose.
What is the Google Play testing requirement?
This is the step that surprises most first-time publishers. Personal accounts created after 13 November 2023 must complete a closed test with at least 12 testers continuously opted in for at least 14 days before applying for production access. Google says the access application usually takes seven days or less to review, but can occasionally take longer. This is separate from the app’s release review (Google Play Console Help). For the full list of what Google Play expects before launch, see our guide to what you need to publish an app on Google Play.
Opening an account does not itself begin the test. Complete app setup, then start a suitable closed test with qualifying testers. The documented requirement is specific to the applicable personal accounts, so check your own Play Console tasks rather than assuming every account has the same path. Keep more than the minimum number of testers opted in, so one person leaving does not leave you short when you apply.
For processing app changes, Google describes a range from a few hours to seven days, or longer in exceptional cases, and recommends allowing a buffer of at least a week between submitting and going live (Google Play Console Help). Treat that as planning guidance, not a maximum turnaround.
The practical lesson is to start this early, not at the end.
How can a small business shorten the timeline?
Most delays are decisions you control. These four changes help most:
- Cut features from version 1. Launch with the one thing users need most, then add the rest once real people are using it.
- Consider a shared codebase where Android and iOS needs are similar, and prototype any device-heavy feature first.
- Name one person who approves decisions. A committee reviewing every screen is a common cause of slow projects.
- Open your Google Play developer account early. Verification and setup can then finish while the app is being built, instead of holding up the release.
If you already have a website, you may be able to reuse its content and structure. One source puts converting an existing website into an app at about 4 to 8 weeks, though it is a single source and depends on the app.
Time and budget are linked, so see our guide to mobile app development cost in India when you plan the budget.
What should I plan for realistically?
For a small business with a focused first version, we would plan like this:
- A focused MVP: plan within the 2 to 4 month range, then confirm what your own scope needs.
- A feature-heavy app, or one with payments, AI features or several integrations: 6 months or more.
- Store release and any required Google Play testing: check whether your estimate already includes them, and add only the work or contingency that is still unresolved.
We found no India-specific timeline data, so these figures come from general industry sources. Your own timeline will depend mostly on scope, how quickly you give feedback and how ready your content and data are.
We build and publish our own apps on Google Play, including MapSeal, a GPS map camera, and Recora, a screen recorder. That is why we put so much weight on testing and store release when we plan a client project. If you want a realistic estimate for your idea, tell us what the first version must do and we will quote it privately.
Frequently asked questions
How long does it take to build a simple mobile app?
A narrow app may fit a few-month plan, but “simple” must describe the complete workflow. Agree whether the estimate includes backend work, testing and release before you compare quotes.
Is it faster to build an app for Android or iOS?
Neither is always faster. Existing code, device features, team experience and release requirements matter more than a blanket platform comparison. A shared codebase can reduce duplicated work where requirements are similar, but supporting both platforms still adds testing.
How long does app store approval take?
Apple says it typically reviews at least 50% of submissions in under 24 hours and 90% in under 48 hours; these are aggregate figures, not a guarantee. Google says processing app changes can take from a few hours to seven days, or longer in exceptional cases, and recommends allowing at least a week. Google’s closed-test production-access application is a separate step.
Can I speed up my app project?
Yes. Reduce the features in version 1, use a shared codebase where it fits, have a single person approve decisions and open your Google Play account early.
Why do agencies give such different timelines?
They define scope differently, and the figures are published to win business. Ask any agency exactly what is included, such as design, testing and store release, before you compare timelines.